Construction Projects
Key 2011 Roads & Water Works Capital Construction Projects
| 1st Kenyon Concession |
| Located between County Rd 34 and Kenyon Dam Rd. The roadway was pulverised, raised approximately 75 mm and double surface treated. There will be some minor ditching involved. Paved entrances were repaved to align with the roadway elevation, other driveways will be gravelled. |
| Little Third Road |
| Brushing along the entire length, ditching will be improved and lower sections of the road will be raised and the entire length re-gravelled. |
| WaterWorks - Centre Street |
| This project is to install a new 150 mm water line that will serve an existing area that is currently serviced by a 40 mm line. This will also improve the fire protection in the area. |
| Elgin Street |
| The sections of roadway on Elgin St between Main and Sinclair St. This is a total reconstruction that involves new storm and sanitary sewers and a new water line. The entire road surface along with curbs and sidewalks will be replaced. Sinclair St will have some water line and asphalt replacement between Kenyon St and St. George St. |